Revised schedule of allocation attached as Appendix 'B'.
Noted with the following comments.
Mr. Beatty stated the C.C.E. was awaiting details of the Pump House from the C.M.&.E.E. an Mr. Stanley would look into this matter.
Mr. Flint reported that the question of the release of the wagon repair road for use as a fuel discharge road had been resolved and the C.C.E. would be advised today. The only alteration was the retention of a siding which would otherwise be removed and in the light of this Mr. Beatty would re-examine the position with a view to the information being supplied to the Planning Officer in June.
Mr. Beatty stated that the depot would be ready in time for the service to start on 12th June, but some small items might still be outstanding. These would not seriously affect the operation of the depot and the work would be completed soon after that date.
Mr. Riley stated the Chief Accountant had not yet received the estimates from the Chief Signal & Telecommunications Engineer and Mr.Flint would ascertain the position.
Mr. Beatty said the Chief Civil Engineer was awaiting approval of the D.T.S. regarding the cross-over roads and Mr.Gould would follow up this matter.
Meeting 84
16th May 1961