-6-
Noted that information requested by Commission was being compiled and would be deaalt with in correspondence. The Chairman requested that in preparation of future schemes for maintenance and servicing facilities, the Chief Mechanical & Electrical engineer be associated with the Director of Traffic Services and submissions be jointly prepared and signed by the two departments.
First part of scheme introduced on June 9th, 1958. Remainder of scheme would be brought into operation on June 15th, 1959.
Scheme partially brought into operation on January 5th, 1959. Anticipated remainder of scheme would be brought into operation in September, 1959.
Full diesel scheme covering greater Birmingham area introduced on November 17th, 1958. Noted that scheme now approved by Area Board and Commission. Scheme for maintenance facilities at Ryecroft also approved by Area Board and Commission.