-3-
First part of scheme introduced on June 9th, 1958. Remainder of scheme would be brought into operation on June 15th, 1959.
Scheme partially brought into operation on January 5th, 1959. Anticipated remainder of scheme would be introduced on June 15th, 1959.
Provisional programme for introduction of diesel service agreed as shown below, and noted no difficulty was anticipated, departmentally, in adhering to this :-
Vehicles from Derby Works Delivery commences Delivery completed |
May 1959 December 1959 |
Training of staff to commence | May 1959 |
Fuelling, inspection and cleaning facilities to be available at Bedford |
June 1959 |
Maintenance facilities at new diesel shed at Cricklewood to be available |
Sept. 14th, 1959 |
Other works - Engineering and signalling between Harpenden and Bedford |
Sept. 14th, 1959 |
Diesel services to be substituted for steam on existing timetables |
Sept. 14th, 1959 |
Full diesel services to be in operation |
January 4th, 1960 |
Commission approval given in principle for preliminary expenditure. Formal submission from departments awaited. Mr.Baker drew attention to the delay previously reported by the Sub-Committee in getting the maintenance portion complete. Mr.Lambert said work was proceeding on the site and although there was some delay, every effort was being made to finish to schedule.