-5-
Scheme to be submitted to General Manager |
May 18th, 1959 |
Scheme to be submitted to Area Board |
June 3rd, 1959 |
Scheme to be submitted to Works & Equipment Committee |
June 23rd, 1959 |
Scheme to be submitted to Commission |
June 25th, 1959 |
Vehicles from Derby Works - Delivery commences Delivery completed |
February, 1960 August, 1960 |
Maintenance facilities at Marylebone Carriage Shed to be available |
February, 1960 |
Other works - lengthening of platforms, etc. to be completed |
March, 1960 |
Diesel services to be substituted for steam on existing timetables as vehicles become available - Commence Complete |
April, 1960 June, 1960 |
New diesel services on the High Wycombe-Aylesbury Line (via W.R.) Commence |
June, 1960 |
Electrification of line between Rickmansworth and Amersham and Chesham (L.T.E.): anticipated date for completion |
September, 1961 |
Quadrupling of line between Harrow and Watford South Junction (L.T.E.); anticipated date for completion |
June, 1962 |
Full new diesel services, including L.T.E. lines; to commence |
June, 1962 |
Agreed that time not yet opportune and Mr.Salmon will keep under consideration.