674.  SCHEMES UNDER CONSIDERATION BY COMMITTEE BUT NOT YET SUBMITTED TO B.T.C.  (Contd.)

1.  Marylebone Suburban Service  (Contd.)

(a) Submission of Scheme  (Contd.)

Scheme to be submitted to General
  Manager
May 18th, 1959
Scheme to be submitted to Area
  Board
June 3rd, 1959
Scheme to be submitted to Works
  & Equipment Committee
June 23rd, 1959
Scheme to be submitted to
  Commission
June 25th, 1959
Vehicles from Derby Works -
  Delivery commences
  Delivery completed

February, 1960
August, 1960
Maintenance facilities at
  Marylebone Carriage Shed
  to be available


February, 1960
Other works - lengthening of
  platforms, etc. to be
  completed


March, 1960
Diesel services to be
  substituted for steam on
  existing timetables as
  vehicles become available -
    Commence
    Complete



April, 1960
June, 1960
New diesel services on the High
  Wycombe-Aylesbury Line
  (via W.R.) Commence


June, 1960
Electrification of line between
  Rickmansworth and Amersham
  and Chesham (L.T.E.):
  anticipated date for
  completion




September, 1961
Quadrupling of line between
  Harrow and Watford South
  Junction (L.T.E.); anticipated
  date for completion



June, 1962
Full new diesel services,
  including L.T.E. lines;
  to commence


June, 1962

(b) Publicity

Agreed that time not yet opportune and Mr.Salmon will keep under consideration.