Departmental representatives reported that programme as shown below proceeding to plan :-
Vehicles from Derby Works Delivery commenced Delivery completed |
May 1959 December 1959 |
Training of staff commenced | May 1959 |
Fuelling, inspection and cleaning facilities to be available at Bedford |
August 1959 |
Maintenance facilities at new diesel shed at Cricklewood to be available |
Sept.28th, 1959 |
Other works - Engineering and signalling between Harpenden and Bedford |
Sept.28th, 1959 |
Diesel services to be substituted for steam on existing timings |
Sept.28th, 1959 |
Full diesel service to be in operation |
Jan.4th, 1960 |
Noted that submission for the new shed had now been received by the General Manager. Mr.Lambert reported that work on the site was generally proceeding according to programme and sufficient facilities would be available to enable service to commence on September 28th.
Noted that the inaugural run with the General Manager, Members of Parliament, local dignitaries and the press was being arranged for September 28th.