664.  SCHEMES AUTHORISED BUT NOT YET IN OPERATION  (Contd.)

2.  Liverpool Lime Street - St.Helens - Wigan Scheme

Scheme partially brought into operation on January 5th, 1959.  Anticipated remainder of scheme would be introduced in June, 1959.

3.  St.Pancras Suburban Scheme

(a) Rolling Stock - Delivery between April and December, 1959.  Part of scheme would be introduced in September, 1959 and complete scheme in January, 1960.  Mr.Stanley will give the Chairman approximate date first train can be sent to St.Pancras for inspection.

(b) Improvements to running facilities between Harpenden and Bedford - Proceeding to programme and will be completed by September, 1959.

(c) Cricklewood Maintenance Depot - Commission approval given in principle for preliminary expenditure.  Formal submission now awaited.  Mr.Baker reported that a draft plan has been sent to the Chief Civil Engineer and he is now awaiting from the Chief Mechanical and Electrical Enginner details of cost of equipment required inside the shed.  Mr.Stanley will pursue.  Work on site proceeding satisfactorily.

(d) Lengthening of platforms - Agreed that Messrs.Gould and Lambert clarify the whole position departmentally (including Signal Engineer).

(e) Closing of stations - Noted that question of closing Napsbury station deferred to the next meeting of the T.U.C.C.

(f) Publicity - Mr.Salmon will pursue in conjunction with departments concerned.  Mr.Pearson suggested that publicity be undertaken in two stages, and Mr.Salmon will report his proposals at the next meeting.

4.  Bletchley - Oxford - Cambridge

Scheme approved by Area Board on February 4th and awaiting Commission approval.

See Minute 660.1(a).